Abstract Cost for estimate and details estimate of Trench for Lift Irrigation Scheme, Length-500 m
S.No
Detail of Items
Dimension
Quantity
Unit
1 Earth Work in Excavation Length 500 m
Length 1640 ft
Top Width 2.5 ft
Bottom Width 2 ft
Depth 3 ft
Cross sectional Area 6.75 CFT
Detail Estimate of proposed Construction of Trench

The Rates of items are based on Schedule of rates (2018- Water Resource Department): Rate of Unskilled Labour- 237.38 Rs/mandays/day : Rate of Skilled Labour- 327.81 Rs/mandays/day
S.No
Item No
Description of Work
Unit
Nos
L (Ft)
B (Ft)
H/D (Ft)
Total Quantity (Sqft/CFT)
In SqM/CM
Rate (Rs)
Amount (Rs)
Labour Cost (Rs)
Material Cost (Rs)
1 6.1.8 Earth Work in excavation of foundation trenches in ordinary soil (Vide classification of soil item-A) and disposal of excavated earth so obtained (50 M away from the edge of the trenches) with initial lead of 150 M and intital lift of 1.5 M as per specification and direction of E/I CM 1 1640 2.25 3 11070 313.78 135.00 42359.69 42359.69 0.00
2 6.1.16 Earth Work in filling foundation trenches or back filling of masonary structures with suitable earth in layers not exceeding 150mm thick well watered, rammed and fully compacted and finally dressed with earth obtained from excavation of foundation trenches and kept at a lead of 30 m and initial lift 1.5 m complete as per specification and direction of E/I CM 1 1640 2.25 3 11070 313.78 87.00 27298.47 27298.47 0.00
3 Contingencies (Signboard, Photography, First Aid box etc.) LS 2500 0.00 2500.00
Total 72158.16
SAY 72158